In the initial stage of preparing a concrete mixing plant, the primary concern of the user is the application procedure for the qualification of the concrete mixing station. Only the approval can be used to establish the station. So what are the processes for the approval of the construction of concrete mixing stations?
1. Business registration (Administration of Industry and Commerce)
Applicants for concrete mixing stations should prepare the application name pre-approval application form, company specific name, shareholder name, total capital contribution, and capital contribution ratio (if the shareholder is a legal person, a copy of the business license is required), capital verification certificate, environmental protection certificate, and property certificate. .
2. Project filing (planning bureau, development and reform commission)
Prepare the project introduction, fill in the project application record form, project record request, copy of the original copy of the business license of the enterprise legal person, and copy of the organization code certificate.
3. Relevant procedures (Environmental Protection Bureau, Construction Bureau, Land Bureau)
Environmental approval, site selection opinion, construction land planning permit, geological disaster assessment report, land evaluation, construction land survey definition report, construction land pre-trial.
4. Apply for land certificate (land bureau)
Cadastral survey form, land application and copy of legal person ID card, company charter and business license, land and resources bureau planning excavation opinion, construction department one certificate, environmental protection certificate, book four plan, land evaluation.
5. Construction procedures before construction (Construction Bureau)
Construction drawing review and approval, construction project approval, construction project planning permit, and bidding.
6. Handling construction permit (construction bureau)
Construction land permit, project report construction form and number, construction project planning permit, bid winning notice, accidental injury insurance policy, drawing review approval, etc.
7. Construction acceptance (audit bureau, construction bureau, fire brigade, meteorological bureau, environmental protection bureau)
Environmental protection acceptance, approval and acceptance, planning and acceptance, lightning protection acceptance, project acceptance, etc.
Environmental protection acceptance, approval and acceptance, planning and acceptance, lightning protection acceptance, project acceptance, etc.
8. Handling property right certificate (housekeeping bureau)
Two copies of the registrant's business license or identity, state-owned land use certificate, construction project planning permit, completion acceptance certificate, and report on building construction area mapping results.
The specific process for the construction approval of the concrete mixing plant is this. Applicants must do the relevant work before applying, avoiding detours and wasting time and energy.